SaferSkills independently audited project-status-report-5dc1c4 (Agent Skill) and scored it 100/100 (green). The audit ran 55 deterministic rules across Security, Supply Chain, Maintenance, Transparency, and Community; it found 0 high-severity and 0 lower-severity findings. The full rule-by-rule trace and per-finding evidence are below. Free, methodology-open.
Findings & checks · 0 flagged
Every scanned point with the score it earned and what moved between them.
First recorded scan — no prior version to compare against.
The primary manifest — the file an agent reads to learn what this artifact does.
Produces a clear, structured project status report — the weekly communication that keeps stakeholders informed without requiring a meeting.
Period: [Date range] | Author: [PM] | Next report: [Date]
| Dimension | Status | Last period | Trend |
|---|---|---|---|
| Overall | Red / Amber / Green | [Last] | Improving / Stable / Declining |
| Schedule | |||
| Budget | |||
| Scope | |||
| Risks |
RAG definitions:
[3-5 sentences. Headline story. If it is Red, say so immediately and why. Never bury bad news after good news.]
| Milestone | Due date | Status | Comment |
|---|---|---|---|
| [Milestone] | [Date] | Complete / At risk / Delayed / On track | [One line] |
Completed this period: [What was delivered] Due next period: [What is expected]
[Issue title] — Critical / High / Low
| Risk | Likelihood | Impact | Mitigation | Owner |
|---|---|---|---|---|
| [Risk] | H/M/L | H/M/L | [Action] | [Name] |
| Decision | Background | Options | Recommendation | Needed by |
|---|---|---|---|---|
| [Decision] | [Context] | [Options] | [Recommendation] | [Date] |
| Budget | Actual to date | Forecast | Variance | |
|---|---|---|---|---|
| Total | £ | £ | £ | £ F/A |
[3-5 specific bullet points — what will happen next period]